Before executing the MRP calculation, the target calculation period must be specified. This can be done by using this parameter.
Calculation period will be from the tomorrow's date to the date specified by this parameter. Please note that today will not be included for MRP Calculation Period. (In other words, if the due date of the sales order has been set today, the quantity required for that order will not be included for MRP calculation)
However, for the sales orders for the MRP controlled Items, Any orders with the due date set prior to this period will be also included as the MRP calculation scope.

All Screens with this Parameter.

Category Screen Section Tab Input Method Mandatory
Production Mgt. MRP Calculation Screen Header (None) Date Input Mandatory